Cooling capacity: the production line bottleneck limiting speed and quality

The drive has capacity to spare, but increasing the speed leads to more rejected bottles. Returning to the previous speed reduces the problem, which may point to cooling on the individual section (IS) machine used to form glass containers. A higher reject rate alone, however, does not prove that the moulds cannot shed heat quickly enough.

Before choosing higher-capacity equipment, separate a thermal limitation from other process changes. For the same container, record speed, cooling settings and defects by section and cavity. Check the weight and temperature of the glass gob too. The number of acceptable bottles produced per hour matters more than cycle speed alone when comparing options.

Faster mechanics cannot make up for a lack of thermal headroom. Production records can help distinguish a cooling constraint from problems with the gob, moulds or process settings.

When cooling, rather than the machine itself, limits production

Cooling becomes a likely constraint when an increase in speed repeatedly affects shape stability or makes differences between cavities more pronounced. Check whether problems appear after the speed change and subside when the previous speed is restored. Operators’ observations are a useful starting point, but should be verified against recorded data.

Note: Slowing the line is not a diagnosis. It may suppress a thermal problem, but it can also conceal another source of instability. If you change both cooling and gob conditions at once, you cannot attribute the result to either adjustment.

Compare runs of the same container, mould set and forming process. Do not assume that findings from blow-and-blow (BB) apply to narrow-neck press-and-blow (NNPB) without checking. Without a baseline recipe, cooling headroom cannot be assessed reliably.

Divide the trial into a baseline record, a controlled change and an assessment under steady operating conditions:

  1. Baseline: Save the recipe version and record speed, cooling settings, gob weight and temperature, mould-set condition, and defects by section and cavity.
  2. Controlled change: Change one predetermined parameter at a time, within approved process limits. Log manual interventions and timing changes.
  3. Steady operation: Separate transitional from steady-state results. Match inspection findings to forming times, allowing for the time containers take to travel through the line.

A defect detected after an adjustment may belong to a bottle formed before it. Without matching results to forming times, the effect of a change can be misread.

Keep recipe management separate from measuring cooling headroom. Check which parameters the system actually records and which it only sets. The name of a controller or the presence of an industrial PC does not, by itself, establish the cause of defects. Consider investment only after repeated comparisons have isolated the effect of cooling from other changes.

How mould cooling works during the forming cycle

A glass gob transfers some of its heat to the mould. The next gob therefore enters a mould whose thermal condition has been affected by the preceding cycle. Shortening the cycle reduces the interval between gobs and, with gob weight and temperature unchanged, increases the heat load on the mould per unit of time. If heat cannot be removed fast enough, the mould’s thermal condition changes; a single measurement will not capture that trend.

The aim is not the coldest possible mould, but the right conditions for forming. Too little, too much or uneven cooling can alter how the glass behaves. Distinguish a shortfall in overall capacity from a local problem: increasing air to an entire section may not correct uneven cooling in one part of a mould and may make other positions harder to set up.

Before investing in a higher-capacity air supply, check the entire cooling path to the mould and relate the findings to cavity results:

  • Air distribution: Check the condition of the supply to each section and any restrictions. Record where pressure and flow are measured.
  • Cooling passages: Check for blockages in accordance with machine documentation and safe maintenance procedures. Link each finding to the relevant section or cavity.
  • Settings at the moulds: Compare affected cavities with the others and establish whether differences relate to cooling rather than a concurrent process change.

Available air-supply capacity is not the same as effective heat removal where the glass contacts the mould. Address identified restrictions in heat removal before judging whether the supply itself needs upgrading.

Illustrative example, not a documented case study: After a speed increase, quality deteriorates in only some cavities. Before increasing the air supply to the whole machine, compare the affected positions with the others and check distribution, passage condition and settings. The cavity pattern helps direct the investigation, but measurements and an assessment of the adjustment are needed to confirm the cause.

When comparing equipment, ask suppliers to specify the conditions under which they assess cooling capacity. Relate settings to the mould set, recipe, container weight and cycle speed; consider both the blank and blow moulds. Make changes in stages so that their effects are not confused with those of another intervention.

What insufficient cooling changes in the cycle and in quality

Lengthening the cycle may restore stability when cooling is insufficient, but it does not remove the underlying cause. Treat it as a reason to investigate. Distinguish inadequate air supply from restricted heat removal in a particular mould. If only some cavities are affected, slowing the whole machine may hide a local cause while unnecessarily limiting production elsewhere.

Do not automatically attribute uneven wall thickness or local thin spots to IS machine cooling. Check the gob, its delivery and the forming settings. Residual stress alone cannot establish whether the cause arose during forming or subsequent thermal treatment. Check the passage through the annealing lehr and its temperature profile; controlled annealing reduces residual stress in the glass. Container-glass manufacturing processes are also described in the European Commission’s Best Available Techniques reference document for the manufacture of glass.

With other conditions held constant, track the same cavities before and after an adjustment. Include these operating measures in the assessment:

  • Acceptable bottles: Measure saleable output over comparable periods using the same inspection criteria.
  • Defects by cavity: Record the extent and type of defects. Distinguish a local finding from deterioration across the machine.
  • Operator adjustments: Log interventions, their frequency and whether they affected the periods being compared.
  • Return to stability: Measure the length of the transition and its losses separately from steady-state operation.

Saleable output over the same period matters, not a higher reading on the machine counter. An economic comparison should therefore include energy, operator time and the ability to sell additional output. Value that output by its contribution margin, not gross revenue, and check whether the speed increase produced usable bottles or simply more rejects.

Why cooling stability matters as well as peak capacity

Peak cooling capacity does not tell you what speed the line can sustain at the required quality. Examine transitions after a cycle-speed increase, a recipe change or a fluctuation in air supply. Your time-based record should include the control demand, actual cooling conditions, speed and defects by section. Identify any missing measurements as gaps in the assessment.

Tip: Compare the cooling system’s actual response, not just its control commands. A valve setting does not demonstrate the flow achieved. A valve at the end of its operating range is a reason to investigate headroom, not a diagnosis in itself.

Compare stable and problematic periods for the same container, looking for changes that precede the defects. Records need enough time resolution to capture the behaviour under investigation; a shift average may hide a transition.

Production capacity is not cooling capacity. A machine rating in tonnes per day does not show how much heat-removal headroom is available for a particular mould set. You also need container details, machine configuration and test conditions.

Ask for capacity comparisons to include a description of the reference equipment and test method. Base an investment brief on the intended production mix, not tonnage alone. Record configuration, speed, cooling and quality for both representative and difficult containers. A successful run of an easy-to-make container does not demonstrate headroom across the range.

Agree the acceptance-test method with the process engineer, maintenance team and supplier before the trial. Define the baseline, the speed or recipe change, how steady operation will be assessed and the quality criteria; set conditions for stopping the test too. The highest speed in one operating mode and the best quality in another do not demonstrate usable capacity.

How to verify cooling headroom before investing

Assess headroom by whether the required speed can be sustained at acceptable quality, not by air pressure alone. Pressure in the main supply does not necessarily describe conditions at the mould. Prepare a record that allows the comparison to be repeated:

  • Production configuration: Specify the container, mould set, forming process and recipe version. Record any configuration changes.
  • Speed and quality: Track cycle time, acceptable output and rejects by section and cavity, applying consistent inspection criteria.
  • Cooling conditions: Record available temperature, flow and pressure data, including measurement locations. Distinguish mould temperature from air temperature.
  • Trial sequence: Log the timing of changes and operator interventions. Separate start-up, transition and steady production.
  • Assessment: Agree stop criteria, defect assessment and responsibility for recording results with the process engineer in advance.

Where operations allow, increase speed in stages while keeping other settings unchanged and staying within pre-approved limits. Mark missing measurements as unknowns, not as evidence that cooling is not the problem. A higher speed without demonstrated quality is not proven headroom.

When selecting equipment, distinguish control features from cooling performance. Recipe management helps preserve settings, but actual conditions need to be demonstrated by measurement. Request a list of sensors, logged variables and data-export options. Repeat the acceptance trial with the same container under comparable conditions, documenting any differences.

Tip: Ask for a sample data export before the trial. Confirm that you can match a settings change to the inspection result by time, and retain the recipe and a log of manual interventions.

Compare a partial upgrade of the existing machine with new equipment in terms of the constraint each option is intended to remove. Check air distribution, moulds and control first; use the findings to justify any wider replacement. The project brief should assign responsibility for safety, documentation and acceptance. The process engineer confirms quality, maintenance confirms practicality, and management agrees an acceptable shutdown period.

Include both benefits and implementation costs in the return-on-investment calculation, using the same assumptions for each option:

  • Additional saleable output: Include only volume that downstream operations can handle and customers can buy. Value it using contribution margin.
  • Energy and maintenance: Use substantiated changes in consumption and costs. Also compare options at the same volume of acceptable output.
  • Implementation: Include installation, measurement, downtime and start-up losses. Separate one-off from recurring costs.

Unused capacity is not additional profit. If downstream operations or demand cannot absorb the increase, do not count it as income in the payback calculation.

Base the decision on a demonstrated bottleneck

Identify IS machine cooling as the bottleneck only after verifying the relationship between speed, mould thermal condition and rejects. Consider the results of a controlled adjustment alongside other possible causes. Air pressure alone is not a sufficient basis for investment. Compare runs of the same container and record settings changes so the effect of cooling is not mistaken for that of another intervention.

The assessment should lead to a specific next step: improve air distribution, adjust the forming process or consider replacing equipment. Agree the criteria with process engineering, maintenance and management beforehand. Decide on the basis of acceptable output and associated costs, not cycle speed alone.

Prepare the evidence for a technical assessment of IS machine cooling. Include the production configuration, recipe, time-stamped record of changes and defects by cavity. Agree the scope of measurement, trial conditions and review date with the supplier. A specific brief makes it possible to assess the actual constraint rather than simply requesting more capacity.

If you would like an independent view of the constraint, we offer a technical hot-end assessment covering BB, PB and NNPB processes.

About the author

Rolf Themann, MBA

Managing Director, T&T Turnov

Rolf Themann, MBA, is Managing Director of T&T Turnov. He has 42 years of experience in mechanical engineering and R&D, rising from designer to technical director and managing director, and has specialised in container glass machinery for more than 22 years. Today, his focus is on driving down energy consumption and total cost per container across the entire hot end.